Skip to main content

Academy · Shop operations

When to reorder film, and what to keep

  • Written lesson. The video is being recorded by our team.
  • For the owner and installers
  • On every plan
  • Checked 2026-11-15

Run out of film and a booked car waits. Overbuy and the money sits on a rack for months. Decide when to reorder film from how fast each product goes and how long your supplier takes, keep only what that number says, and use the remnants a job leaves behind before you open a fresh roll.

The steps

  1. Find how many feet a week each product uses

    Take the last two months of film logged against jobs for one product and divide by the weeks. Do it for the products you sell most first.

  2. Ask how long delivery takes

    From the day you order to the day the roll is on your rack. Use the slow weeks, not the good ones.

  3. Set the reorder point

    Feet per week times the weeks delivery takes, plus a safety margin for a busy week. Type it into Reorder threshold (ft) on the product.

  4. Order when the banner says so

    When the feet left fall to the threshold, the product shows Reorder and the Reorder soon banner appears. Create purchase order starts an order with every low product on it. Tick Email me when film runs low if you would rather hear about it.

  5. Use remnants first

    Before cutting a mirror cap or a door edge from a new roll, check the remnants. Mark used when one is gone.

  6. Look for dead stock each quarter

    The inventory report's Dead stock figure shows film that has not moved. Stop reordering it, and use it up or sell it off.

What this lesson leaves out. The reorder point is only as good as the film logged against jobs; unlogged cuts make every product look slower than it is. Supplier minimums and price breaks can justify a bigger order, and this lesson does not weigh them.

On every plan.

Read the lesson as it will be spoken

There are two ways to get film wrong. Run out, and a car that was booked for Thursday sits waiting for a roll. Overbuy, and a few thousand dollars sits on the rack doing nothing. The fix for both is one number per product: the point at which you reorder.

Work it out from two things. How many feet a week that film goes through, from the last couple of months of jobs. And how long your supplier takes, from order to roll on the rack, on a slow week.

As an example, a film you use forty feet a week, with a two week delivery. That is eighty feet. Add a margin for a busy week, say thirty feet. Reorder at a hundred and ten. Put that number on the product, and the shop tells you when you hit it, instead of you finding out from an empty core.

Then the offcuts. A good remnant is film you already paid for. Before anyone cuts a mirror cap off a new roll, check the remnant shelf.

And once a quarter, look at what has not moved. Film that sat there all season is money you cannot spend on anything else. Stop reordering it, and find a way to use it up.

Three questions

Each answer is in the lesson above. Pick one to see why.

  1. 1.In the example, a film uses 40 feet a week and delivery takes two weeks. With a 30-foot safety margin, what is the reorder point?
  2. 2.What happens when a product's feet left reach its threshold?
  3. 3.Where should a small piece come from first?

More on this path

For every setting it touches, read the help guide: Inventory and rolls.

For what the feature does in a shop, see film inventory software.

Worth reading after it: How to track film inventory and Film waste calculator.

Wrap shops

Set up quoting by panel and by roll, and keep the film you stock in step.

  1. Wrap shop setup: by the panel and the roll
  2. Track film rolls by the foot
  3. When to reorder film, and what to keep
  4. What film waste costs you in a year

Every lesson in the Service VIN Academy